Natural gas installation continues to tie up Armdale roundabout

Work continues around the Armdale Roundabout to install natural gas lines. Councillor Linda Mosher tweeted earlier this week about the installation, saying that Heritage Gas had changed their plans without HRM approval. This caused some lengthy traffic tie-ups. Mosher says the company was told they could only close a lane in the circle for one day, but she later tweeted she discovered the company had a lane closed contrary to its permit. She says she will pursue a fine under city bylaws. On September 27, the city posted the following two PSAs about the work:  -----HRM citizens are advised work continues on the installation of a new natural gas main through the Armdale Roundabout. The contractors have completed the pipe installation in the area and are now moving on to site reinstatement. Due to the availability of some materials, this work cannot be completed at night.The reinstatement will take place on weekdays from 9 a.m. to 4 p.m., with unrestricted hours on weekends. During construction, all approaches to the Roundabout will be reduced to one lane. This is necessary to avoid conflicts where motorists may have to change lanes in the Roundabout as exit lanes are affected by this work. Motorists approaching the circle must yield to all traffic in the circle.The anticipated construction schedule is as follows:Friday, September 28 – Concrete curb work on Chebucto Road and Herring Cove Road approach and exit lanesSaturday, October 6 and Sunday, October 7 (if required) – Asphalt work on Chebucto Road at the approach and exit lanes, and Herring Cove Road from the Roundabout to Purcells Cove Road.The paving on Herring Cove Road will result in traffic being reduced to one lane. This is expected to cause considerable delays in the area on Saturday and Sunday, October 6-7. Motorists are encouraged to use alternate routes where possible.------ HRM citizens are advised work continues on a new natural gas main through the Armdale Roundabout toward Regatta Point. Pipe installation on Purcells Cove Road from Herring Cove Road to Spinnaker Drive will require traffic to be reduced to one lane. This work is restricted to weekdays between the hours of 9 a.m. to 4 p.m. This section is currently under construction and is expected to continue until Thursday, October 4.Throughout the remainder of the project – Purcells Cove Road from Spinnaker Drive to Anchor Drive – two lanes of traffic will be maintained at all times.All work will be completed by Heritage Gas’s contractor, Sackville Trenching Limited.Heritage Gas and HRM apologize for any inconvenience.Contact:Ernest Douglas, Construction InspectorHeritage Gas229-7023Derek FlahertySackville Trenching877-0537Heritage Gas Customer Service1-866-313-3030HRM Right of Way Services490-6240...
Work continues around the Armdale Roundabout to install natural gas lines. Councillor Linda Mosher tweeted earlier this week about the installation, saying that Heritage Gas had changed their plans without HRM approval. This caused some lengthy traffic tie-ups. Mosher says the company was told they could only close a lane in the circle for one day, but she later tweeted she discovered the company had a lane closed contrary to its permit. She says she will pursue a fine under city bylaws. 
On September 27, the city posted the following two PSAs about the work:  
—–
HRM citizens are advised work continues on the installation of a new natural gas main through the Armdale Roundabout. The contractors have completed the pipe installation in the area and are now moving on to site reinstatement. Due to the availability of some materials, this work cannot be completed at night.
The reinstatement will take place on weekdays from 9 a.m. to 4 p.m., with unrestricted hours on weekends. During construction, all approaches to the Roundabout will be reduced to one lane. This is necessary to avoid conflicts where motorists may have to change lanes in the Roundabout as exit lanes are affected by this work. Motorists approaching the circle must yield to all traffic in the circle.
The anticipated construction schedule is as follows:
Friday, September 28 – Concrete curb work on Chebucto Road and Herring Cove Road approach and exit lanes
Saturday, October 6 and Sunday, October 7 (if required) – Asphalt work on Chebucto Road at the approach and exit lanes, and Herring Cove Road from the Roundabout to Purcells Cove Road.
The paving on Herring Cove Road will result in traffic being reduced to one lane. This is expected to cause considerable delays in the area on Saturday and Sunday, October 6-7. Motorists are encouraged to use alternate routes where possible.
——
 HRM citizens are advised work continues on a new natural gas main through the Armdale Roundabout toward Regatta Point. Pipe installation on Purcells Cove Road from Herring Cove Road to Spinnaker Drive will require traffic to be reduced to one lane. This work is restricted to weekdays between the hours of 9 a.m. to 4 p.m. This section is currently under construction and is expected to continue until Thursday, October 4.
Throughout the remainder of the project – Purcells Cove Road from Spinnaker Drive to Anchor Drive – two lanes of traffic will be maintained at all times.
All work will be completed by Heritage Gas’s contractor, Sackville Trenching Limited.
Heritage Gas and HRM apologize for any inconvenience.
Contact:
Ernest Douglas, Construction Inspector
Heritage Gas
229-7023
Derek Flaherty
Sackville Trenching
877-0537
Heritage Gas Customer Service
1-866-313-3030
HRM Right of Way Services
490-6240

Source: http://www.outsidethecircle.ca/index.php?option=com_content&view=article&id=365:natural-gas-installation-continues-to-tie-up-armdale-roundabout&catid=1:latest-news&Itemid=50

Favorite Fall Trends

Favorite Fall Trends

Weekend Wrap-up: Sept 29-30, 2012