Natural Gas Installation – Main Street (Dartmouth)

Friday, Nov. 21, 2014 (Halifax, NS) – Halifax Regional Municipality is advising residents and motorists that work will begin Monday (Nov. 24) to extend the natural gas main on Main Street between Gordon Avenue and Hartlen Street.

The pipe installation and subsequent restoration work is expected to take approximately two weeks. Lane drops will be in place, but a minimum of one lane in each direction is expected to be maintained at all times.

No work will take place between the morning and afternoon rush hours (7 a.m. to 9 a.m., and 4 p.m. to 6 p.m., Monday to Friday).

Motorists should expect delays and are asked to use alternative routes whenever possible.

Heritage Gas and the municipality apologize in advance for any inconvenience this work may cause.

Source: Release

About Haligonia.ca

See news happening near you? Tell us. Click here to email our team.

 

The views and opinions expressed in this content are those of the author and do not necessarily reflect those of haligonia.ca.

You might also like...

Weekly Traffic Advisories

NEW WORK
---

LUNENBURG COUNTY: Martins Brook Bridge

Martins Brook Bridge, Trunk 3, approximately 900 metres north of Hermans Island Road, is closed for bridge replacement until Friday, Feb 19.

Detour on Trunk 3 to Fauxburg Road,...

Leave a Reply

Your email address will not be published. Required fields are marked *