Northern Pulp Stack Testing Underway

A second set of stack tests at the Northern Pulp mill have begun.

Testing started Oct. 15 and is expected to conclude by Friday, Oct. 24. The Environment Department will get results from the tests within 30 days after they are finished.

Stantec Consulting Ltd. is doing the stack tests, which are required as part of the ministerial order issued to the company Aug. 21.

Results are expected to show if work during the September
shutdown reduced emissions and addressed a problem with the Pictou County mill’s power boiler.

The company is on target to replace the precipitator, which should reduce emissions at the plant to within limits, as required in the ministerial order.

Results from the August stack tests can be found at http://www.novascotia.ca/nse/issues/northern-pulp-boat-harbour.asp .

FOR BROADCAST USE

     A second set of stack tests at the Northern Pulp mill are

underway.

Testing started October 15th and is expected to be

finished by Friday (October 24th).

     The results are due in November and should show if work

during the mill’s September shutdown has reduced emissions and

addressed a problem with the power boiler.

     The stack tests are required as part of the ministerial

order issued to the company August 21st.

Source: Release

Re-Jigged: A celebration of all things Celtic from October 24 to 26

Anchor from HMCS Niobe Uncovered