Today Federal Ministers offered an update on the AOPS Project.The first 2 of 7 phases of the 288 million definition contract were completed on time and on budget. This contract was announced in March 2013.

Today Federal Ministers offered an update on the AOPS Project.
The first 2 of 7 phases of the 288 million definition contract were completed on time and on budget. This contract was announced in March 2013.

an additional 2 phases of the 7 phases have now authorized, valued at 53 million. (presumably phases 3 and 4) Phases 3 and 4 Include 

Engineering Design Phase 2 – This task will include the system engineering activities, integrated logistical support analysis and supplier engagement activities that are necessary to demonstrate that the Arctic/Offshore patrol ship design is a complete and integrated solution that meets all the contract design specification requirements with acceptable risk and within the cost and schedule constraints. 

Engineering Design Phase 3 – This task will include the system engineering activities, integrated logistic support analysis and supplier engagement activities that are necessary to demonstrate that the Arctic/Offshore patrol ship design is a complete and integrated solution that meets all of the contract design specification requirements and is ready for the start of vessel construction.

No Number of vessels has been set yet  – So it still stands at the vague 6-8